Team Size Can Be
the Key
to a Successful Project

Doug Putnam
QSM Vice President
The Research
People frequently ask if
there is an optimum staffing level for a software development
project? At one extreme, the number of people could
be below a critical mass and the project is vulnerable
to the loss of a key person. Very small teams are also
highly dependent on the skills of the "individual".
At the other extreme, large teams experience human
communication complexities. Large teams quickly gravitate
toward the average skill set of the group. Somewhere
in the middle there should be an optimum situation.
So, the quick and dirty answer to the question is;
yes there is an optimum team size, but it is dependent
on a number of variables. Some obvious variables are:
- The size of code to
be developed and reused
- The application complexity
- The degree to which
schedule or cost is the overriding schedule constraint
In this research, we set
out to find the optimum staffing for a specific application
domain and size regime. In this work we will define
optimum staff size as the team size most likely to
achieve the highest productivity, the shortest schedule,
the cheapest cost with the least amount of variation
in the final outcome.
Our Method
To minimize the variables
that could impact our results we decided to select
a set of medium sized information systems that were
completed in the last 3 years. Medium sized was defined
as products that contained 35,000 to 95,000 new or
modified source lines of code. There were 491 projects
that satisfied the conditions. The sample was then
stratified into team size groupings, which is shown
in Figure 1. Notice that all of the data sets are fairly
well distributed across the entire size regime. The
average size of all 5 data sets is 57,412 ESLOC. None
of the data set averages are more that 3,000 SLOC away
from the overall average size.

The Results
The average productivity,
schedule and effort were analyzed for each of the data
sets along with the standard deviation. We plotted
the averages and compared them to see which had the
best performance and observed overall trends if they
were apparent.
Productivity Data
The average Productivity
Index (a measure that uses size, schedule time and
development effort in it's calculation) was calculated
for each of the 5 data sets. The Productivity Index
for the 1.5-3, 3-5 and 5-7 person data sets were very
similar and had the highest level of efficiency. The "smaller
teams" were 2 or more Productivity Indices higher
than the "larger teams". The 5-7 person data
set had approximately 9% less variation than the 3-5
person projects and 12% less variation compared to
the 1.5 - 3 person projects. The variation is displayed
using the high-low bars which represent one standard
deviation from the average.

Schedule Data
The schedule data shows
that there is a decreasing trend in schedule performance
as the team sizes get larger until the team size reach
9-11 people where the average time starts to increase.
The schedule performance data show the 5-7 person data
set as having the best performance, however the 3-5
person data set is a very close second.

Effort Data
The development effort
statistics show that larger teams translate into more
effort and cost. The trend appears to have a exponential
behavior. The most cost effective strategy is the smallest
team, however the extreme non-linear effort increase
doesn't seem to kick in until the team size approaches
9 or more people.

Conclusions
The goal of our research
was to find optimum team size for building medium sized
information systems. From the 491 projects that were
analyzed we would conclude that a 3-7 person team has
the best performance (3-5 would be the best, but 5-7
people is a very close second). The 3-5 person data
set was not the outright winner in any of the assessment
categories however it had very good performance in
all areas. One can speculate on why we see this behavior
on the moderately small teams, but common sense suggest
the following reasons:
- This team size provides
some protection against the loss of a key person.
- Individual performance
is not overcome by group dynamics.
- Team size is probably
close to optimum in building motivation and cohesion.
- There is minimum human
communication complexity among team members.
- It doesn't require significant
management overhead.
Next time you are planning
a project think hard about the optimum staffing levels
because it can clearly have a significant impact on
the overall results. This study gives you some insights
into an application and size domain where many systems
are being built today. Coupled with good peopleware
practices you should be able to make a real impact
on your organization's bottom line performance.