Performance Benchmark Tables

Average Project Performance

The following reference tables provide summary performance data (schedule, effort, staff, quality, and productivity) for typical projects from QSM’s Real Time, Engineering, and IT software databases.  This information provides a high level, quick reference for benchmarking both completed projects and software estimates.

All project data supplied in these tables comes from QSM’s historical database of over 8000 completed projects.  The QSM database is a cornerstone asset utilized in all of our consulting service engagements.  It represents the largest and most complete set of validated and completed software project data in the world. 

Although this information is provided free of charge to the general public, QSM also offers custom consulting services and a benchmarking consortium to address specialized research and analysis needs. 

Demographics and Descriptive Data

  • The data in the tables represents projects completed after the year 2000.
  • Duration , effort, and average staff include activities from requirements determination through initial release.
  • Mean Time to Defect is determined during the first 30 days of system operation.
  • Projects are segregated into groups by primary application type:
  • The Business group includes business (IT) systems.
  • The Engineering group includes: command & control; system software; telecommunications; scientific; and process control.
  • The Real time group includes: avionics; real time; microcode & firmware.

 

Group Size New & Modified SLOC (ESLOC) Schedule (months) Effort (Person Months) Average Staff (FTE) Mean Time to Defect (Days) SLOC / PM
Business 1,000 4.5 6.1 1.4 8.1 163.9
Business 10,000 6.9 24.2 3.5 3.5 413.2
Business 100,000 10.1 95.1 9.4 1.5 1051.5
Business 500,000 13.5 247.3 18.3 0.9 2021.8
             
Engineering 1,000 4.9 10.2 2.1 7.6 98.0
Engineering 10,000 8.7 43.5 5.0 3.1 229.9
Engineering 100,000 16.0 188.9 11.8 1.3 529.4
Engineering 500,000 24.0 530.7 22.1 0.7 942.2
             
Real Time 1,000 4.6 10.2 2.2 35.1 98.0
Real Time 10,000 10.7 76.0 7.1 6.7 131.6
Real Time 100,000 25.7 570.3 22.2 1.3 175.3
Real Time 500,000 47.9 2339.9 48.8 0.4 213.7
             
             
             
Group Size Function Points Schedule (months) Effort (Person Months) Average Staff (FTE) Mean Time to Defect (Days) FP / PM
Business 100 6.6 18.8 2.8 6.5 5.3
Business 500 8.5 48.2 5.7 2.9 10.4
Business 1,000 9.6 77.9 8.1 2.0 12.8
Business 5,000 12.7 215.4 17.0 0.9 23.2
Business 10,000 14.3 328.6 23.0 0.6 30.4