Staff Replan Capability in SLIM-Control

Staff Replan Capability in SLIM-Control

 

Can I use the forecast function to explore various staffing options?

When you run a forecast, SLIM-Control bases the future staffing profile on the peak staff and staffing shape defined in the current plan.

While Phase 3 is ongoing, run a tradeoff forecast to see the impact of increasing or decreasing staff and apply any resulting schedule tradeoff to your existing forecast.  To run a tradeoff forecast, select Control | Tradeoff Forecast… from the menu.

Once Phase 3 has completed, use the maintenance forecast to evaluate staff tradeoffs.  The maintenance forecast can only be performed during Phase 4.  To run a maintenance forecast, select Control | Run Forecast… from the menu.

Taxonomy upgrade extras 
SLIM-Control Staffing